CAG expresses displeasure over dismal performance
of renewable energy sector in Maharashtra
Asks state to step up efforts for introduction of
competitive bidding for tariff
The Comptroller & Auditor General (CAG) of India has expressed
displeasure over the Maharashtra government for dismal performance in the renewable energy (RE) sector especially due to delay in
the release of solar energy development policy, lack of execution of energy
purchase agreements and violation of the statutory provision due to diversion
of fund. In its report for the year ended March 31, 2015, CAG observed that despite huge potential of solar power in the state, the solar sector was not tapped due
to absence of suitable policy framework of the government.
CAG, which conducted performance audit of RE sector during 2007-08 and
2014-15, said the government had not declared solar policy till June 2015 and
in its absence a nominal target of 275 MW was fixed by Maharashtra Energy Development Agency (MEDA) based on the
achievement of solar power projects commissioned in the previous years. Against
the target of 275 MW, projects of 325.25 MW were developed. "Due to non
framing of policy, the solar sector had long been ignored and the capacity
addition in this sector was insignificant despite a potential of 64,320 MW assessed
by the ministry of New and Renewable Energy,'' CAG viewed. CAG's observations
come when the Centre with the active participation of states proposes to add
1,75,000 MW in the RE sector by 2022.
In case of wind energy, CAG said 50 wind energy projects were
commissioned during April 2014 and March 2015. The wind generators generated
68.42 million units (MUs) (April to May 2015) and fed energy into the grid of
Maharashtra State Electricity Distribution Company (MahaVitaran). However, MahaVitaran did not
execute energy purchase agreements with these 50 generators in January 2016
mainly due to high tariff. CAG has asked MahaVitaran and Maharashtra State
Electricity Transmission Company (MahaTransco) to continue their efforts with
the Maharashtra Electricity Regulatory Commission (MERC) for introduction of
competitive bidding for tariff determination for the wind energy sector.
The auditor has asked the state government, MEDA and water resources
department to ensure development of identified 59 wind and 60 small hydro sites
after conducting feasibility study. However, CAG suggested that MahaVitaran and
MahaTransco need to devise a system to ensure timely reimbursement of
expenditure incurred by the developers on evacuation infrastructure.
''Due to shortfall of 2004 MUs in purchase of solar and non solar energy
from RE operators which worked out to 7.14% of the target, the MahaVitaran may
be required to deposit Rs 260.33 crore in the renewable purchase obligation
(RPO) in regulatory fund as per the directive of MERC,'' CAG said.
Further, CAG noted that the state government collected Rs 2,315 crore by
way of tax on sale of electricity during 2007-08 and 2014-15. The government
was required to transfer the same amount to MEDA but only Rs 112.79 crore was
transferred. ''The balance of Rs 2,202.21 crore was neither transferred to MEDA
nor utilized for promotion of the RE sector. This resulted in diversion of the
fund in violation of the statutory provisions,'' CAG remarked.
Happy Investing
Source:Moneycontrol.com
No comments:
Post a Comment